The Department of Energy’s Office of Project Assessment recently issued its final CD-4 Review Report on the Energy Sciences Network (ESnet)’s ESnet6 upgrade project. The review, held on July 12 – 13, 2022, and conducted at the request of Barbara Helland, Associate Director of Science for Advanced Scientific Computing Research (ASCR), assessed the project’s readiness to proceed to the approval of project completion. The project completed all threshold key performance parameters (KPPs) six months ahead of the early finish date, two years ahead of the CD-4 Level 1 milestone date, and well under budget. The committee assessed that the project was ready to proceed to CD-4 approval, which was achieved on July 29, 2022. The Final Closeout report and Lessons Learned are being submitted next week within the specified 90-day window.
“I want to congratulate the entire ESnet organization especially the ESnet6 project director, Kate Mace, and the project team,” said Inder Monga, executive director of ESnet. “When the team set out to deliver on a project scope as vast as the ESnet6 launch, we did not imagine a global pandemic would interrupt the process. Despite that, the team delivered the entire project ahead of the deadline and, even with supply-chain issues, managed to complete the scope below the projected budget. Most of the team attended the ESnet6 Unveiling Event on October 11 and heard their accomplishments praised by the lab directorate as well as congresspeople and DOE staff.”
The committee commended the project team for their “unique and innovative approach” in completing the project objectives and complimented ESnet for their agility in following through with the project scope while dealing with the difficult environment generated by the COVID-19 pandemic. The report stated that COVID-19 restrictions, limitations, and supply-chain issues presented “no significant impact” on the project’s critical path. The report also identified the distributed nature of operations and ESnet’s support for a remote workforce as an “invaluable” approach and a best practice to be shared beyond the DOE complex.
The final reports required for the official Project Closeout will be submitted to DOE this week. The ESnet team has continued to keep up the pace as they work toward additional enhancements to the ESnet6 Facility. “The #ESnet6Week festivities the week of October 9 energized the team. Not only were the project accomplishments celebrated at the ESnet6 Unveiling event, but the team also heard firsthand about the impact the project has already had on scientific discovery,” said Kathryn Mace, the ESnet6 project director, and Network Engineering group lead. “Hearing about the expansion of scientific collaborations made easier with the ESnet6 network and automated operations provided the team with newfound motivation to keep moving full speed ahead. ESnet6 sets the foundation for global scientific innovation over the next 10 years.”
You must be logged in to post a comment.